Skip to main content

First Year Tower Residence Hall

Scheduled to open in August 2028, the 18-story First Year Tower will house 972 students, bringing the entire first-year class together in one location. The building is designed to achieve Passive House certification, reflecting Wentworth’s commitment to sustainability through ultra-efficient design that reduces energy use while enhancing comfort and performance. The ground floor will feature public-facing spaces, including a dining area and student lounge, supporting campus life while also serving the surrounding community.

First Year Tower Rendering from the Front - students walk by a tall modern looking dorm with glass windows and trees in the courtyard

Quick Facts

Number of Stories
18

First Year Tower will include 18 occupied stories.

Passive House Standards

The building is designed to meet Passive House standards.

Number of Beds
972

The residence hall will house our entire first year class.

Number of Alumni
49

To date, 49 Wentworth alumni have worked on the project.

Key Information

We appreciate your patience as construction gets underway, and we will continue to share project updates as work progresses.

  • Milestone Dates

    12.02.2026 – Tower Crane Installation
    12.14.2026 – Begin Vertical Structure Construction 
    01.01.2027 – Begin Dining Space Construction
    03.04.2027 – Material Hoist Installation
    10.01.2027 – Begin Elevator 
    02.11.2028 – Weathertight,  Begin MEP Startups
    02.16.2028 – Tower Crane Removal
    03.23.2028 – Material Hoist Removal
    06.05.2028 – Begin MEP Commissioning
    08.15.2028 – Substantial Completion

  • Construction Hours

    Standard Construction hours are Monday through Friday from 7:00 AM to 6:00 PM, with construction activity typically occurring between 7:00 AM and 4:00 PM.  Occasional Saturday work will typically take place between 7:00 AM and 3:00 PM.

Renderings

View renderings of the First Year Tower Residence Hall

From the Field: Construction Update

A view of piles being driven for the First Year Tower from above

Updated September 10, 2026

Construction of the First Year Tower continues to make significant progress. The work scheduled during September focuses primarily on underground infrastructure, foundation construction, and preparation for the building's vertical structure. Crews will continue installing essential underground utilities to support the new residence hall, including electrical service, water, sewer, and drainage systems. This work includes installation of several utility access structures and connections that will serve the building. A major milestone this month is the installation of the building's underground fuel storage tank. Activities include excavation, concrete foundation placement, delivery and crane installation of the tank, connection of associated piping systems, required inspections, and final backfilling. Community members may notice increased activity from excavation equipment and periodic crane operations during this work. Foundation work becomes a primary focus throughout September. Workers will continue excavation and construction of pile caps, grade beams, foundation mats, and reinforced concrete elements that will support the residence hall structure. Multiple concrete pours are scheduled over the coming weeks, along with deliveries of reinforcing steel. Preparations for the project's tower crane will begin, including construction of the crane foundation and installation of temporary power infrastructure. Once operational, the tower crane will support future structural construction activities. The project team is also constructing a full-scale exterior mock-up featuring precast concrete panels, windows, curtain wall elements, louvers, and granite finishes. This mock-up will be reviewed by the City of Boston and project stakeholders to confirm appearance and quality before full installation begins.

Outside the Fence: Construction Impact

Construction map on campus

Please be advised that construction of the new building's facade mockup will take place outside of Ira Allen at the location shown in red on the adjacent site plan. This work will continue through September, and pedestrian access will be maintained in and around the buildings.  Significant impacts to overall parking availability are not anticipated, but a small number of parking spaces will be temporarily unavailable for several days during the last week in September.  The mockup will remain in place until the completion of the project in August 2028.

News

Contact Us

For questions or concerns regarding construction activity contact: newresidencehall@wit.edu or 617-387-3400.

In case of emergency, dial 911 or Wentworth Police: 617-989-4444. 

First Year Tower Rendering from the Front - students walk by a tall modern looking dorm with glass windows and trees in the courtyard

Developed in Partnership With

Balfour Beatty Campus Solutions
Perkins&Will
BOND