Skip to main content

First Year Tower Residence Hall

Scheduled to open in August 2028, the 18-story First Year Tower will house 972 students, bringing the entire first-year class together in one location. The building is designed to achieve Passive House certification, reflecting Wentworth’s commitment to sustainability through ultra-efficient design that reduces energy use while enhancing comfort and performance. The ground floor will feature public-facing spaces, including a dining area and student lounge, supporting campus life while also serving the surrounding community.

First Year Tower Rendering from the Front - students walk by a tall modern looking dorm with glass windows and trees in the courtyard

Quick Facts

Number of Stories
18

First Year Tower will be 18 stories high.

Passive House Standards

The building is designed to meet Passive House standards.

Number of Beds
972

The residence hall will house our entire first year class.

Number of Alumni
48

To date, 48 Wentworth alumni have worked on the project.

Key Information

We appreciate your patience as construction gets underway, and we will continue to share project updates as work progresses.

Over the next few months, you can expect the following activities:

  • Milestone Dates

    09.08.2026 – Begin Foundations
    09.17.2026 – Pile Driving Complete
    12.02.2026 – Tower Crane Installation
    12.14.2026 – Begin Vertical Structure Construction 
    01.01.2027 – Begin Dining Space Construction
    03.04.2027 – Material Hoist Installation
    10.01.2027 – Begin Elevator 
    02.11.2028 – Weathertight,  Begin MEP Startups
    02.16.2028 – Tower Crane Removal
    03.23.2028 – Material Hoist Removal
    06.05.2028 – Begin MEP Commissioning
    08.15.2028 – Substantial Completion

  • Construction Hours

    Typical Construction hours are Monday through Friday from 7:00 AM to 6:00 PM, with construction activity occurring between 7:00 AM and 4:00 PM.

    Saturday work will typically take place between 7:00 AM and 3:00 PM

    Please note: through mid-September 2026, early morning deliveries are planned between 5:00 AM and 7:00 AM to avoid peak commuter hours. 

Renderings

View renderings of the First Year Tower Residence Hall

From the Field: Construction Update

A view of piles being driven for the First Year Tower from above

Updated August 3rd, 2026

Throughout August, work at the Pike Residence Hall project will focus on completing critical utility, infrastructure, and site preparation activities. Steam line relocation work for existing buildings will continue with installation, testing, insulation, and backfilling of the new steam and condensate lines. Utility crews will advance sewer, water, storm drainage, and electrical duct bank installations, including overnight work within the site and a planned water connection at Huntington Avenue. Crews will also complete restoration of the Edwards/Rodgers walkways, including paving, grading, and temporary site finishes. Site development activities include excavation for the stormwater infiltration system and the underground fuel storage tank (which serves the new building's generator), as well as asphalt removal and excavation for pile caps, grade beams, and the tower crane foundation. Additional project activities include installation of end-bearing steel piles, and setup and commissioning of the BOND office trailer complex near the corner of Huntington Ave and Ruggles Street.

This month will also see the start of construction of the exterior building mockup, which will serve as a full-scale test installation of key exterior building components before façade construction begins on the residence hall building. The mockup will include the slab-on-grade foundation, structural backup steel, a representative precast concrete panel with window, and the associated louver assembly. By constructing and reviewing these elements in advance, the project team can verify the appearance, fit, alignment, material quality, weatherproofing details, and constructability of the exterior envelope. Any necessary adjustments can be identified and incorporated before full production and installation, helping to reduce risk, avoid rework, and ensure the final building meets design and performance expectations.

Outside the Fence: Construction Impact

Construction map on campus

Façade Mockup Construction

Please be advised that throughout August, construction of the new building's facade mockup will take place outside of Ira Allen at the location shown in red on the adjacent site plan.  Pedestrian access will be maintained in and around the buildings.  Parking availability will not be affected during the first two weeks of August. Later in the month, a small number of parking spaces will be temporarily unavailable for several days as construction activities progress. We do not anticipate significant impacts to overall parking availability.

News

Contact Us

For questions or concerns regarding construction activity contact: newresidencehall@wit.edu or 617-387-3400.

In case of emergency, dial 911 or Wentworth Police: 617-989-4444. 

First Year Tower Rendering from the Front - students walk by a tall modern looking dorm with glass windows and trees in the courtyard

Developed in Partnership With

Balfour Beatty Campus Solutions
Perkins&Will
BOND