Skip to main content

First Year Tower Residence Hall

Scheduled to open in August 2028, the 18-story First Year Tower will house 972 students, bringing the entire first-year class together in one location. The building is designed to achieve Passive House certification, reflecting Wentworth’s commitment to sustainability through ultra-efficient design that reduces energy use while enhancing comfort and performance. The ground floor will feature public-facing spaces, including a dining area and student lounge, supporting campus life while also serving the surrounding community.

First Year Tower Rendering from the Front - students walk by a tall modern looking dorm with glass windows and trees in the courtyard

Quick Facts

Number of Stories
18

First Year Tower will be 18 stories high.

Passive House Standards

The building is designed to meet Passive House standards.

Number of Beds
972

The residence hall will house our entire first year class.

Number of Alumni
48

To date, 48 Wentworth alumni have worked on the project.

Key Information

We appreciate your patience as construction gets underway, and we will continue to share project updates as work progresses.

Over the next few months, you can expect the following activities:

  • Milestone Dates

    09.08.2026 – Begin Foundations
    09.17.2026 – Pile Driving Complete
    12.02.2026 – Tower Crane Installation
    12.14.2026 – Begin Vertical Structure Construction 
    01.01.2027 – Begin Dining Space Construction
    03.04.2027 – Material Hoist Installation
    10.01.2027 – Begin Elevator 
    02.11.2028 – Weathertight,  Begin MEP Startups
    02.16.2028 – Tower Crane Removal
    03.23.2028 – Material Hoist Removal
    06.05.2028 – Begin MEP Commissioning
    08.15.2028 – Substantial Completion

  • Construction Hours

    Typical Construction hours are Monday through Friday from 7:00 AM to 6:00 PM, with construction activity occurring between 7:00 AM and 4:00 PM.

    Saturday work will typically take place between 7:00 AM and 3:00 PM

    Please note: through mid-September 2026, early morning deliveries are planned between 5:00 AM and 7:00 AM to avoid peak commuter hours. 

Renderings

View renderings of the First Year Tower Residence Hall

From the Field: Construction Update

A view of piles being driven for the First Year Tower from above

Updated July 1, 2026

Over the next several weeks, construction activities will focus on completing critical underground infrastructure, utility installations, and site preparation work. Crews will continue steam utility installation and testing, including welding, pressure testing, insulation, and backfilling operations, while also advancing water, sewer, storm drainage, and electrical utility connections throughout the site. Work will continue at Ruggles Street, Huntington Avenue, and the areas surrounding the MassArt Tree House and Edwards/Rodgers buildings, with a combination of daytime and limited nighttime construction activities to safely complete utility tie-ins and minimize disruption. In addition, crews will complete walkway and entrance improvements at Edwards/Rogers, including waterproofing, grading, concrete sidewalk installation, asphalt paving, and final site restoration. Preparations will also begin for the next phase of construction, including deep foundation pile installation, office trailer setup, temporary power work, and construction mock-up development. These activities represent important milestones in preparing the site for the start of major building construction.

Outside the Fence: Construction Impact

A map which shows the location of the utility work on Huntington Ave, there is a sign that says the sidewalk is closed at the crosswalks on Huntington and right in front of the treehouse building on Huntington.

Utility Work at Huntington Avenue - Update

Please be advised that utility work occurring at the sidewalk and into Huntington Avenue will be now performed during the day between 9:00 AM and 3:00 PM throughout this week. During this time, a section of the sidewalk may be closed, and pedestrian traffic will be routed across Huntington Avenue. 
 

News

Contact Us

For questions or concerns regarding construction activity contact: newresidencehall@wit.edu or 617-387-3400.

In case of emergency, dial 911 or Wentworth Police: 617-989-4444. 

First Year Tower Rendering from the Front - students walk by a tall modern looking dorm with glass windows and trees in the courtyard

Developed in Partnership With

Balfour Beatty Campus Solutions
Perkins&Will
BOND