First Year Tower Residence Hall
Scheduled to open in August 2028, the 18-story First Year Tower will house 972 students, bringing the entire first-year class together in one location. The building is designed to achieve Passive House certification, reflecting Wentworth’s commitment to sustainability through ultra-efficient design that reduces energy use while enhancing comfort and performance. The ground floor will feature public-facing spaces, including a dining area and student lounge, supporting campus life while also serving the surrounding community.
Quick Facts
First Year Tower will be 18 stories high.
The building is designed to meet Passive House standards.
The residence hall will house our entire first year class.
To date, 48 Wentworth alumni have worked on the project.
Key Information
We appreciate your patience as construction gets underway, and we will continue to share project updates as work progresses.
Over the next few months, you can expect the following activities:
-
Milestone Dates
09.08.2026 – Begin Foundations
09.17.2026 – Pile Driving Complete
12.02.2026 – Tower Crane Installation
12.14.2026 – Begin Vertical Structure Construction
01.01.2027 – Begin Dining Space Construction
03.04.2027 – Material Hoist Installation
10.01.2027 – Begin Elevator
02.11.2028 – Weathertight, Begin MEP Startups
02.16.2028 – Tower Crane Removal
03.23.2028 – Material Hoist Removal
06.05.2028 – Begin MEP Commissioning
08.15.2028 – Substantial Completion -
Construction Hours
Typical Construction hours are Monday through Friday from 7:00 AM to 6:00 PM, with construction activity occurring between 7:00 AM and 4:00 PM.
Saturday work will typically take place between 7:00 AM and 3:00 PM
Please note: through mid-September 2026, early morning deliveries are planned between 5:00 AM and 7:00 AM to avoid peak commuter hours.
Renderings
View renderings of the First Year Tower Residence Hall
From the Field: Construction Update
Updated July 1, 2026
Over the next several weeks, construction activities will focus on completing critical underground infrastructure, utility installations, and site preparation work. Crews will continue steam utility installation and testing, including welding, pressure testing, insulation, and backfilling operations, while also advancing water, sewer, storm drainage, and electrical utility connections throughout the site. Work will continue at Ruggles Street, Huntington Avenue, and the areas surrounding the MassArt Tree House and Edwards/Rodgers buildings, with a combination of daytime and limited nighttime construction activities to safely complete utility tie-ins and minimize disruption. In addition, crews will complete walkway and entrance improvements at Edwards/Rogers, including waterproofing, grading, concrete sidewalk installation, asphalt paving, and final site restoration. Preparations will also begin for the next phase of construction, including deep foundation pile installation, office trailer setup, temporary power work, and construction mock-up development. These activities represent important milestones in preparing the site for the start of major building construction.
Outside the Fence: Construction Impact
Utility Work at Huntington Avenue - Update
Please be advised that utility work occurring at the sidewalk and into Huntington Avenue will be now performed during the day between 9:00 AM and 3:00 PM throughout this week. During this time, a section of the sidewalk may be closed, and pedestrian traffic will be routed across Huntington Avenue.
News
A Home for Every First-Year Student: New Tower Rises at the Heart of Campus
City Approves Wentworth's Master Plan Amendment and New Community Agreement
Contact Us
For questions or concerns regarding construction activity contact: newresidencehall@wit.edu or 617-387-3400.
In case of emergency, dial 911 or Wentworth Police: 617-989-4444.
Developed in Partnership With